Energy regulation in China involves a number of stakeholders including various governmental authorities that heavily regulate the energy sector, monopolistic state-owned enterprises (SOEs), private companies that are trying to catch up, foreign companies that have had varying degrees of success, and a vast number of consumers. Currently, and for the foreseeable future, energy regulation in China is anchored in China's ambitious economic restructuring agenda. Top priority is being placed on environmental goals and the deployment of cleaner energy in China's economic reform plan. The ‘energy revolution' proposed in the 13th Five Year Plan for National Economic and Social Development (2016 to 2020) is divided into three main sections, namely the upgrade of the energy structure, the development of energy transmission network, and the establishment of a smart energy internet.

China, as one of the largest economies globally, is also deeply embedded in the global energy value chain; therefore, the effects of China's energy consumption and production extend well beyond its borders.

China's prominent role in the global energy market underlines the importance of understanding China's domestic energy regulation regime and its market structure. This chapter aims to provide an overview of China's energy market and regulatory regime with a focus on oil and gas, power, and renewable energy from a foreign investment perspective. We have endeavoured to state China's energy regulation and practice on the basis of the materials available to us as of April 2017.


i Regulators
Oil and gas

The Ministry of Land and Resources (MLR) is responsible for the supervision and administration of the exploration and exploitation of mineral resources throughout China. It has the authority to grant the licences required for the exploration and production of crude oil and natural gas in China. It also plays a role in examination and approval of blocks open to foreign investment.

The National Development and Reform Commission (NDRC) is in charge of setting out and implementing policies in respect of the oil and gas sector. It is also responsible for approving certain investment projects. The National Energy Administration (NEA) was established under the NDRC, with broad duties ranging from drafting energy strategies, proposing reform advice, implementing the management of energy sectors to approving overall development plans (ODP) for a specific oil or gas project.

The Ministry of Commerce (MOFCOM) was previously in charge of review and approval of making, and amendments of, all production-sharing contracts (PSCs). This approval is no longer required, and instead record filing at MOFCOM is necessary.


The NDRC also has the authority to approve certain investment projects in the power industry.

The Market Regulatory Department of the NEA (which took over from the State Electricity Regulatory Commission) regulates the power industry. It is responsible for the enactment and enforcement of regulations in this industry, and also for granting power business permits to power companies.

Other regulators

Other regulators include:

    • a the Ministry of Environmental Protection (MEP): takes charge of administering and enforcing environmental protection matters in China;
    • b the National Nuclear Safety Administration: an authority under the MEP that acts as the central government agency responsible for regulating nuclear safety, supervising all civilian nuclear infrastructure in China. It also inspects nuclear safety activities and regulates the approval mechanism; and
    • c the State Administration of Work Safety: responsible for overseeing and administering work safety nationwide.
ii Laws and regulations

China has many laws and regulations governing its energy sector, including:

Oil and gas
  • a The Mineral Resources Law (1986, amended 1996 and 2009) and its Implementation Rules (1994) establish the basic legal framework under which exploration and production activities (including oil and gas development) are to be carried out.
  • b The Oil and Natural Gas Pipeline Protection Law (2010) provides for the security requirements for the construction and operation of pipelines.
  • c The Regulation on Registration of Exploitation of Mineral Resources (1998, amended 2014) provides detailed requirements on the registration of mineral resources exploitation and the issuance of exploitation licences.
  • d The Measures for the Administration of Transfer of Mineral Exploration Rights and Exploitation Rights (1998, amended 2014) regulate the transfer of exploration rights and exploitation rights.
  • e The Regulation on Sino-foreign Cooperation in the Exploitation of Onshore Petroleum Resources (1993, amended 2001, 2007, 2011 and 2013) is the basis for foreign companies to participate in the exploration and exploitation of onshore blocks in China through PSCs.
  • f The Regulation on Sino-foreign Cooperation in the Exploitation of Offshore Petroleum Resources (1982, amended 2001 and 2013) is the basis for foreign companies to participate in the exploration and exploitation of offshore blocks in China through PSCs.
  • g The Measures for Regulation of Fair and Open Access to Oil and Gas Pipeline Facilities (2014) (Third-party Access Measures) provide the third-party access regime, allowing third parties to use the surplus capacity of pipeline facilities.
  • h Measures for the Administration of Natural Gas Pipeline Transportation Prices (for Trial Implementation) (2016) provide that the pipeline transportation price is determined by the price administration department under the State Council following the principle of ‘allowed cost plus reasonable profits'.
  • i Measures for the Supervision and Review of Natural Gas Pipeline Transportation Pricing Costs (for Trial Implementation) (2016) provide that the price administration department under the State Council shall be in charge of the supervision and review of pipeline transportation pricing cost following the principle of legality, the principle of relevance and the principle of rationality.
  • a The Electric Power Law (1996, amended 2009 and 2015) is the main legislation governing the electricity sector.
  • b The Circular on the Reform Plan for Power Prices (2003) sets out the targets for the power price reform and is followed by the Regulation on Feed-in Tariffs (2005), the Regulation on Power Sales Price (2005) and the Regulation on Transmission and Distribution Price (2005).
  • c The NDRC Notice on Pilot Reform of Transmission Tariff in Shenzhen (2014) and NDRC Notice on Further Reform of Transmission Tariff following the Zhongfa [2015] No. 9 Document (2015) regulate the ongoing transmission tariff reform.
  • d The Regulations on Electricity Regulation were issued in 2005 to strengthen and improve electricity regulation, focusing on maintaining the order of electricity markets and promoting the development of the electric power industry.
  • e The Administrative Regulations on Permits for the Power Industry (2005) focus on maintaining the order of the electricity markets and promoting the development of the electric power industry.
  • f The Opinions regarding Further Reform of the Electric Power Regime (2015) set out the plan for further reform.
  • g The NDRC and NEA Circular on Issuing Supporting Documents for Electric Power System Reforms (2015) provides implementation measures for the reform of the power regime.
  • h The NDRC and NEA Circular on Issuing Administrative Measures on Electricity Companies' Entrance and Exit and Administrative Measures on Orderly Derestricting the Electricity Distribution Network Business (2016) provide opportunities for social capital to enter into the electricity distribution industry.

In addition, there are numerous regulations and rules enacted by various administrative authorities, to define specific procedures or particular issues with respect to the electricity sector under the framework of the main law and regulations.

  • a The Energy Conservation Law (2008, amended 2015) is aimed at promoting energy conservation.
  • b The Renewable Energy Law (2010) sets general principles on renewable energy.
  • c The NDRC Notice on Feed-in Tariff for Offshore Wind Power (2014) provides for the feed-in tariff for offshore wind farms.
  • d The NEA Notice on Facilitating the Development of Geothermal Power (2013) is aimed at promoting the development and utilisation of geothermal power.
  • e The NDRC Notice on Feed-in Tariffs for Onshore Wind Power and Photovoltaic Power Generation Projects (2015) provides for the feed-in tariff for onshore wind farms and solar energy projects.
  • f The Administrative Regulation on Guaranteed Purchase of Renewable Energy-generated Power in Full Amount (2016) sets out detailed rules to guarantee the purchase of renewable energy generated power (excluding hydropower).
  • g The Rules for Issuing and Free Trading Green Power Certificate (2017) provide for the regime of issuing and free trading of Green Power Certificates.
iii Regulated activities
Oil and gas

As mentioned above, exploration and production activities are subject to exploration and exploitation licences issued by the MLR.

In upstream oil and gas exploration and exploitation, foreign companies should partner with and enter into PSCs with legally designated national oil companies (for details, see Section II.iv, infra).

Pipeline design and construction is subject to review based on criteria related to safety, environmental protection, optimal land use and economic feasibility. The construction of oil and gas pipeline networks must be approved by the NDRC or its local branches. The qualifications of the enterprises and personnel engaged in the design, installation, use and inspection of pipelines must be accredited by the General Administration for Quality Supervision, Inspection and Quarantine or its local counterpart as the case may be.

A business permit is required to engage in crude oil storage or trading; or refined oil wholesale, retail or storage.


Power companies are required to obtain electric power business permits issued by NEA. Electric power business permits are divided into three categories depending on the type of business:

  • a a power generation permit for power generation companies;
  • b a power transmission permit for power transmission companies; and
  • c a power supply permit for power supply companies.

A company applying for an electric power business licences must demonstrate that it has the financial capability and personnel with the required experience. In addition, power companies must obtain approval for each specific power project from relevant authorities and comply with environmental regulations to be issued with the electric power business licence.

Exemptions are available for the power generation permit. The NEA granted the following power plants by notice issued in April 2014:

  • a distributed generation projects registered or approved by the NEA;
  • b small hydropower stations with single-station generating capacity below 1MW;
  • c new-energy generation projects such as solar, wind, biomass, ocean power and geothermal power with generating capacity below 6MW;
  • d power projects with comprehensive use of heat and pressure by-products; and
  • e captive power plants without direct combustion of fossil fuel and that are dispatched by dispatching organisations at city level or below.
iv Ownership and market access restrictions
Oil and gas

The state has ownership over all mineral resources within the territory of China. Pursuant to the Mineral Resources Law, a licensing regime has been adopted and the MLR has the authority to grant exploration licences and production licences. Applicants for exploration licences or exploitation licences must be approved by the State Council to engage in oil and gas exploration and production activities. The approved companies are national oil companies (NOCs) and include China National Petroleum Corporation (CNPC), China Petrochemical Corporation (Sinopec) and China National Offshore Oil Corporation (CNOOC). However, the state has been integrating energy reform in Xinjiang province since November 2016, which includes reducing market access restriction. In particular under the reform, the state will further encourage diversified entities to enter into oil and gas exploration and production activities. It remains to be seen whether such trial reform will successfully introduce more private capital into the upstream sector.

Foreign companies can partner with designated Chinese oil companies (usually CNPC, Sinopec or CNOOC) through the PSC regime to invest in onshore and offshore exploration and production in China.

Regarding unconventional oil and gas, exploration and exploitation of coalbed gas generally follows the regime for conventional oil and gas - exploration licences and exploitation licences are granted to designated companies and foreign companies can invest through the PSC regime. Both the licencing regime and PSC regime, however, apply to shale gas exploration and exploitation by foreign investors. Foreign companies can partner with Chinese companies holding an exploration licence of a shale gas block or establish a joint venture with a Chinese partner to bid for the licences directly.

The Foreign Investment Industrial Guidance Catalogue (the Catalogue) is issued by the NDRC and MOFCOM, setting out encouraged, restricted and prohibited activities and sectors. Any activity or sector not included in the Catalogue is permitted. Projects that are encouraged benefit from simpler approval procedures and can also benefit from customs incentives. Restricted activities and sectors must generally be approved at higher levels of government, which means that approvals can be harder to obtain. Sino-foreign joint venture cooperation in the exploration and development of shale gas is ‘encouraged' under China's current Foreign Investment Industrial Guidance Catalogue (2015). This allows foreign investment in shale gas to receive certain tax and administrative benefits. MOFCOM's Notice on Development Plan of Shale Gas has an additional requirement that foreign investors should have expertise in the exploration and production of shale gas. Neither the Catalogue nor the Notice requires Sino-foreign joint ventures to be majority controlled by Chinese partners; however, this is a requirement in the MLR's second bid round. Accordingly, under the current regime, a Sino-foreign joint venture engaged in shale gas extraction must be controlled by the Chinese partner or partners. However, as the PSC regime is more established through the conventional oil and gas cooperation, in practice, most sino-foreign cooperation on shale gas exploration and exploitation still follows the PSC regime. The State Council issued new measures to expand the opening-up and positive utilisation of foreign capital in January 2017, including relaxing the entry restrictions on foreign investors in unconventional oil and gas (e.g., oil shale, oil sands and shale gas). In addition, the new draft Catalogue issued in December 2016 for public comment until 6 January 2017 (the 2016 Catalogue draft) proposed new market entry opportunities for special oil and gas: exploration and development of oil shale, oil sands and shale gas will not be limited to Sino-foreign equity joint ventures and Sino-foreign cooperative joint ventures.

The midstream oil and gas industry, however, is dominated by NOCs. CNPC controls nearly all the long-distance pipelines in China, including the West-East Pipeline. The CNPC website shows that the CNPC's crude oil and natural gas pipelines in China accounted for nearly 70 per cent and 78 per cent of the nation's total respectively by the end of 2014. In December 2015, CNPC combined a sprawl of pipeline operations in a single company with a registered capital of 80 billion yuan, aiming to improve efficiency and boost the value of the businesses. It is considered a step towards potential divestment in future, as well as a prologue to the government's bigger plan to reform the energy regime in China, including to strip oil companies of their pipeline assets and set up a national pipeline company or regional pipeline companies that would own and operate oil and gas pipelines.

Construction of new imported LNG receiving terminals is subject to central government approval. Most of the LNG terminals are owned and operated by NOCs. In recent years, private entities as well as foreign entities have started to participate in this sector as well. Currently, there is one LNG terminal in operation that has been established by private investment, and two in construction. See Section III.ii, below, for details of third-party access to infrastructure.

The downstream oil and gas sector is still dominated by NOCs. Sinopec has focused on downstream activities, such as refining and distribution, with these sectors making up over 70 per cent of the company's revenues in recent years.


The main market players in the power industry include power companies (among which the five large state-owned generators are China Huaneng Group, China Datang Corporation, China Huadian Corporation, China Guodian Corporation and China Power Investment), grid companies (namely, State Grid Corporation of China and China Southern Power Grid Co.), and ancillary companies engaged in power engineering and construction (China Energy Engineering Group Co. and Power Construction Corporation of China).

The main opportunities for foreign investors in the power industry lie in the construction and operation of power stations with certain technologies and renewable energy. Specifically, the following types of business in the power industry are ‘encouraged' in the Catalogue:

  • a construction and operation of ultra-supercritical power stations with single unit power of 600,000kW or more;
  • b construction and operation of power stations for heat-power co-generation units of back-pressure (extraction-back) type, heat-power-cool multi-generation units, and heat-power co-generation units of 300,000kW or more;
  • c construction and operation of power stations with large air-cooled generation units with single unit power of 600,000kW or more in regions suffering from water shortage;
  • d construction and operation of projects of power generation via integrated gasification combined cycle and other clean coal power generation projects;
  • e construction and operation of power generation projects with single unit power of 300,000kW or more that use fluidised bed boilers and coal gangue, middling, and coal slurry;
  • f construction and operation of hydropower stations for the primary purpose of power generation;
  • g construction and operation of nuclear power stations (the Chinese party must hold a controlling interest);
  • h construction and operation of new-energy power stations (including solar energy, wind energy, geothermal energy, tidal energy, wave energy and biomass energy); and
  • i construction and operation of a power grid (the Chinese party must hold a controlling interest). This was previously a ‘restricted' item under the 2011 Catalogue.

The Catalogue restricts the following two types of power plants connected to small grids:

  • a power plants utilising coal-fired and steam condensation thermal generator sets whose single generator capacity is 300,000kW at most; and
  • b thermoelectric power stations utilising coal-fired steam condensation and extraction thermal generator sets whose single generator capacity is 100,000kW at most.

The above types of power plants (in the case of thermoelectric power stations, the capacity threshold is 200,000kW) connected to large grids fall into the prohibited category for foreign investment. However, according to the 2016 Catalogue draft, foreign investment into the above types of power plants would be removed from the ‘restriction' and ‘prohibition' categories.

v Transfers of control and assignments

The transfer of exploration rights and exploitation rights for non-oil or gas resources is allowed provided that the following conditions are met:

  • a two full years have passed since the issue of the exploration licence, or the discovery of the mineral resources available for further exploration or exploitation in the exploration zone; or one full year has passed since the exploitation enterprise began exploitation;
  • b the specified minimum input for exploration has been fulfilled;
  • c no disputes have arisen regarding the ownership of the exploration rights and exploitation rights;
  • d the exploration right usage fees, exploitation fees or any price for the exploration and exploitation rights have been paid; and
  • e a transferee of mineral exploration rights or exploitation rights should meet the qualifications of a mineral exploration right applicant or exploitation right applicant prescribed in the Measures for Area Registration Administration of Mineral Resources Exploration and Survey or the Measures for the Registration Administration of Mineral Resources Exploitation.

The MLR will decide whether to approve the transfer within 40 days after receipt of the application. The transfer contract will take effect as of the day of approval.

There is no regulatory requirement for transfer of participating interest under a PSC. Previously, any amendments to the PSC were required to be approved by MOFCOM. This requirement was abolished in 2013 and now only record filing with MOFCOM is required. In practice, Chinese PSCs often provide that the consent of a foreign investor is required if the NOCs propose to take over the production operations before foreign contractors full recovery of the development costs. After the full recovery of the development costs incurred in accordance with the ODP of any oil or gas field within the contract area, the NOCs may, at any time, have the right by giving a written notice to the foreign contractor to take over the production operations.

Transfer of power generation units in operation requires a change to the power business licence, which shall be approved by the NEA. The NEA will review if the requirements for granting the relevant licences are satisfied.


i Vertical integration and unbundling

The State Grid and China Southern Grid control the transmission, distribution and sale of power in China. Under the current power regime, grid companies purchase power from power generation companies at the regulated feed-in tariffs and sell power at the regulated power sales prices.

The ongoing power price reform, however, aims to separate the sale of power from grid companies. The Opinions regarding Further Reform of the Electric Power Regime (2015) and the NDRC and NEA Circular on Issuing Supporting Documents for Electric Power System Reforms (2015) provide that power generators will enter into agreements directly with retailers or users with term contracts or spot trades, with the power price being freely negotiated between the parties. The transmission tariff will be regulated by the government on a ‘cost plus reasonable profits' basis. According to the Notice by the NDRC regarding Comprehensive Promotion of Pilot Reform of Transmission and Distribution Tariff (2016), this reform is now carried out in most provinces.

Since 2009, the user-generator direct trading system has been put on trial in more than 20 provinces. Companies with high electricity consumption (such as aluminium electrolysis and steel plants) can purchase electricity directly from generators. The price paid by such consumers is composed of the power purchase price negotiated between the generator and the consumer (under a power purchase contract), the transmission and distribution price paid to the grid company (under a service contract) and government surcharges. The Opinions regarding Further Reform of the Electric Power Regime (2015) also set out further goals for the development of this user-generator direct trading system.

ii Transmission/transportation and distribution access
Oil and gas

China established the third-party access scheme in the Third-party Access Measures for a trial period of five years. In addition, The Regulation on Construction and Operation of Natural Gas Infrastructure (2014) encourages investment into natural gas facilities.

Under the Third-party Access Measures, pipeline and facility operators should equally open pipeline networks and associated facilities to third parties if operators have surplus capacity and, in the case of multiple users, non-discrimination principles should apply, but priority should be given to contracts already in place. The facilities to be opened include not only trunk pipelines and branch pipelines for crude oil, refined oil and natural gas, but also the relevant associated facilities including ports, receiving terminals, and liquefaction, compression and storage facilities.

The Third-party Access Measures also state that pricing authorities should decide the service fee for such access. It remains to be seen how the Measures will be implemented in practice. We also note that a new policy is likely to be issued by Chinese government, which allows all oil and gas players access to natural gas infrastructure owned by national oil companies. It is therefore worth keeping an eye on the latest developments.


A grid operator must ensure non-discriminatory and fair opening of its grid to qualified power plants and disclose the following information to power plants within its network:

  • a grid structure and line layouts;
  • b amount and status of transformation facilities;
  • c total installed capacity;
  • d power supply and demand and transmission capacity of major lines and outgoing lines; and
  • e tariffs and prices for inter-provincial power transactions and direct trading.

An interconnection agreement will be entered into by the grid operator and the power generator, specifying terms and conditions including capacity and feed-in tariff.

Grid companies must ensure non-discriminatory and fair access to their grid to qualified power plants.

For renewable power generation (RPG) enterprises, the grid operators are required to:

  • a build and manage the interconnection system for qualified RPG projects;
  • b enter into grid connection agreements with qualified RPG enterprises; and
  • c purchase all the on-grid power generated by these RPG projects at a higher feed-in tariff.
iii Rates
Oil and gas

According to Measures for the Administration of Natural Gas Pipeline Transportation Prices (for Trial Implementation) (2016) and Measures for the Supervision and Review of Natural Gas Pipeline Transportation Pricing Costs (for Trial Implementation) (2016), pipeline transportation fees are regulated by the NDRC using the principle of ‘allowed cost plus reasonable profits'.


In theory, the rates that the grid companies charge end users seek to recover power purchase costs and fees for transportation, distribution and sale services, power losses and the like. However, in practice, the rates are set by the government and vary depending on the type of user and the region.

iv Security and technology restrictions

Oil and gas pipeline owners and operators have obligations under the Oil and Natural Gas Pipeline Protection Law, including those to patrol, inspect and maintain the pipelines; to upgrade, transform or stop using those pipelines that do not satisfy the safe use requirements in a timely manner; to post, repair or change signs related to the pipeline; and to take effective safety protection measures for a pipeline not in operation.

As gas pipelines are considered to be ‘specialised equipment' under the specialised equipment regulatory regime, a pipeline operator is required to hold a Specialised Equipment Registration Certificate. In addition, both natural gas and gas pipelines are considered to be ‘hazardous material' under the hazardous material regulatory regime. The ‘producer' of hazardous material is required to hold a Production Safety Permit and the ‘trader' of hazardous material is required to hold a Hazardous Material Operation Permit. However, it is not clear whether the pipeline owner and operators will be considered producer or trader of hazardous material.

Power grid operators also have security obligations under the Electricity Law. The power grids shall be operated in accordance with the principles of safety, high quality and economy. Power grid operations must be maintained in an uninterrupted and stable way, with a stable supply of electricity guaranteed.


i Development of energy markets

The price of product oil and natural gas is regulated by the NDRC. However, as the State Council clearly pointed out in its notice regarding lowering real economic business costs in August 2016, one of the essential plans is to liberalise the prices in competitive sections (in particular, to speed up market-oriented reform in oil and natural gas).

As mentioned above, under the current regime, grid companies purchase power from power generation companies at regulated fixed prices and sell power to the customers at regulated fixed prices. Generation is dispatched on a fair and equal basis.

Under the ongoing power price reform, the Chinese government is exploring the possibility of opening up electricity markets. The aim at this stage is to establish a mid-to-long-term market and a spot market.

ii Energy market rules and regulation
Oil and gas

To engage in crude oil storage or trading, or refined oil wholesale or retail, a business permit issued by MOFCOM is required. There are certain requirements for applicants to obtain a business permit, including a certain amount of registered capital, long-term supply agreements, and stable sales channels and facilities. Foreign-invested enterprises may also apply for permits.

State trading enterprises and non-state trading enterprises may engage in the importation of crude oil and refined oil. MOFCOM publishes a list of state trading enterprises, and companies outside that list may become a non-state trading enterprise if they:

  • a have a foreign trade business qualification;
  • b satisfy the requirements published by MOFCOM; and
  • c register with MOFCOM.

Both state trading enterprises and non-state trading enterprises must obtain an import licence issued by MOFCOM. However, non-state trading enterprises shall be subject to import quotas. This quota for the year 2017 is 87.6 million tonnes. In 2015, MOFCOM also issued a notice setting out the detailed requirements for refineries to import crude oil, including requirements regarding equipment, product quality, safety management and personnel.

Use of imported crude oil was previously limited to NOCs. In February 2015, however, the NDRC issued a notice breaking the monopoly. Local refineries can now apply to use imported crude oil if they meet certain requirements, including requirements regarding equipment, product quality and safety management. Twenty-one refineries have obtained a permit from the NDRC to use imported crude oil so far.

There is no market entry restriction on the import or export of gas.

In addition, trading of oil and gas requires safety permits under, for example, the hazardous material regulatory regime.


Sale of power to customers is currently largely controlled by the State Grid and China Southern Grid through their subsidiaries. Under the power price reform, however, we expect to see more participants in the market. Apart from the user-generator direct trading system, the NDRC and NEA Circular on Issuing Supporting Documents for Electric Power System Reforms (2015) also allows independent power supply companies to participate in the market provided that certain conditions, including on total assets, equipment and expertise, and the electric power business licence issued by NEA, are met.

iii Contracts for sale of energy
Oil and gas

There are two types of government regulated prices:

  • a government fixed price; and
  • b government guidance price.

The former is fixed and there is no flexibility, while the latter is more flexible. Government guidance price can be in the form of:

  • a a benchmark price with a float range;
  • b maximum price;
  • c minimum price;
  • d the rate of price difference; and
  • e the profit rate.

When a foreign company invests in upstream oil and gas through the PSC regime, parties would normally agree in the PSC that the NOC will sell the foreign investor's share of oil and gas on its behalf. Usually the price is determined by reference to the prevailing price in an arm's-length transaction for a long-term sales contract of similar quality of crude oil in the main world oil markets with adjustment to be made for quality, delivery, transportation, payment and other terms, and expressed as ‘free on board' price at the delivery point in China

Upstream crude oil prices and gas prices are not regulated, while refined oil prices and natural gas prices at city gate are subject to government regulation:

  • a the retail and wholesale of gasoline and diesel, as well as sale of gasoline and diesel to wholesale business, railway customers and transportation customers are subject to the governmental guidance price; and
  • b the supply of gasoline and diesel for state reserves or Xinjiang Production and Construction Corps as well as the factory price of aviation gasoline and aviation diesel are subject to government (regulated) pricing.

The price of gasoline and diesel will be adjusted every 10 business days based on international crude oil price, processing cost, taxes, transmission fees and reasonable profits.

The government caps the price of natural gas at the city gate while the ex-factory price can be negotiated between parties. The prices of shale gas, coalbed gas, coal gas, liquefied natural gas and fertiliser gas are determined freely by suppliers and consumers. In order to accelerate the gas price reform, the state started a trial regime in Fujian province in November 2016. According to such trial regime, the city gate price will be decided based on negotiation between suppliers and consumers, which means it will not be subject to the government guidance price.


Power prices are set by the government, taking into account the power purchasing cost, the loss from power transmission and distribution, power transmission and distribution price and government funds. The prices vary depending on a number of factors including season, peak hour, region and type of user (namely, residential user, agricultural user and industrial and commercial user).

Customers are allowed to participate in the power market if certain criteria are met, and may choose to enter into power purchase agreements with (1) power supply companies, or (2) directly with power generators. The terms and conditions of these agreements can be freely negotiated between two parties.

The Opinions regarding Further Reform of the Electric Power Regime (2015) and the NDRC and NEA Circular on Issuing Supporting Documents for Electric Power System Reforms (2015) set out future steps to further facilitate the reform, including determining qualified generators based on energy conservation and environment protection requirements; expanding the direct trading to power supply companies; and encouraging long-term agreements between generators and customers.


As part of government policies in response to climate change and in line with China's commitments to the international community, the State Council set an objective to control energy consumption to 5 billion tonnes of standard coal in the 13th Five-Year Plan period (2016 to 2020). The NDRC also set Mid and Long Term Plans for renewable energy development: 10 per cent of the total energy consumption should be sourced from renewable energy by 2010, and 15 per cent by 2020. The midterm target (10 per cent by 2010) has been achieved.

In addition, the Chinese government has established a clean development mechanism fund to support construction and industrial activities that are beneficial to strengthen proper responses to climate change since 2010. The construction and operation of power stations using renewable energy is encouraged under the 2015 Foreign Investment Catalogue.

Under the current power regime, the government sets higher feed-in tariffs (FITs) to encourage power generation from renewable energy. The table below sets out the feed-in tariffs for wind, biomass and solar power.

Electricity source



Onshore project: four tiers ranging from 0.4 yuan/kWh to 0.57 yuan/kWh, depending on project locations (for projects approved after 1 January 2018 and projects approved before 1 January 2018 but not in construction at the end of 2019).

Offshore projects: 0.85 yuan/kWh or 0.75 yuan/kWh depending on the distance to shore.


0.75 yuan/kWh.


Three tiers ranging from 0.65 yuan/kWh to 0.85 yuan/kWh, depending on project locations.

Other incentives include:

  • a surcharges collected from end users, which are used to subsidise the difference between feed-in tariffs and the benchmark price for desulfurised coal generators, operations and maintenance for independent public power systems, and costs for connecting renewable energy generators to power grids;
  • b favourable loans with financial discounts for renewable energy projects listed in the guidance catalogue for renewable energy industry development;
  • c subsidies for renewable energy development in areas such as new-energy vehicles, building-integrated solar photovoltaic systems, wind turbines and biomass power generation; and
  • d tax incentives.

Also, the NDRC approved a nuclear project in March 2015 marking the official relaunch of nuclear projects in China. The Mid and Long-Term Development Plan of Nuclear Power by the State Council set the target for nuclear power at installed capacity of 58 million kW and 30 million kW under construction by 2020, which means a shortfall of 39 million kW. The industry is expecting a large wave of investment into nuclear power in the near future. In March 2016, Shenhua, China's largest coal producer, was reported to be in talks with leading Chinese nuclear developers China National Nuclear Corporation and China General Nuclear Power Corporation on taking stakes in domestic nuclear projects, as part of its efforts to diversify into cleaner forms of energy.

In order to help reduce government subsidies to the renewables sector, the NDRC, together with the Ministry of Finance and the NEA, issued a Circular on the Trial Implementation of the Renewable Energy Green Power Certificate Issuance and Voluntary Subscription Transaction System (the Green Power Certificate Circular) in January 2017. According to the Green Power Certificate Circular, solar and wind power producers would apply for and be issued tradeable certificates for the renewable electricity generated by them. Renewable energy users are encouraged to buy such certificates at an agreed price through negotiation or a bidding process. Solar and wind power producers who have sold their certificates would no longer receive a direct subsidy for the corresponding electricity. The NDRC have indicated that the state may launch a mandatory green certificate scheme in 2018.


The G20 Energy Ministerial Meeting was held at the end of June 2016, on the subject of ‘building a low-carbon, intelligent and shared energy future'. It is one of the most important measures since China signed the Paris Agreement, a treaty dealing with greenhouse gases emissions mitigation, on 22 April 2016. The Paris Agreement has been approved by the Standing Committee of the National People's Congress and came into force on 4 November 2016.

In line with China's above commitment to the international community, the State Council released the 13th Five Year Plan for Energy Development (2016 to 2020) in February 2017, listing future energy strategies for an efficient, clean and safe energy system. According to the Plan, the annual primary energy consumption will be capped at an amount equivalent to 5 billion tonnes of standard coal by 2020. The Plan sets goals on future energy structure, with at least 15 per cent of energy supplied from non-fossil fuels, 20 per cent supplied from natural gas and at most 58 per cent from coal by 2020.

China also continues towards achieving the marketisation of its energy supply. On the one hand, after publishing regulations on transportation pricing for natural gas pipelines in October 2016 and starting a trial regime regarding the marketisation of a city gate natural gas price in the Fujian province, the Chinese government made big steps in natural gas price reform. On the other hand, as encouraged by the NEA, NOCs published details of their oil and gas infrastructure - a material development in opening access to oil and gas pipeline facilities. At the same time, the ongoing power price reforms have enjoyed sweeping progress. In September 2016, the NDRC significantly expanded the scope of a pilot provincial power grid in light of the transmission and distribution price reforms. In addition, pilot programmes for the reform of the electricity sale sector have also been expanded. After the establishment of the Beijing Electricity Trading Centre and the Guangzhou Electricity Trading Centre in March 2016, more and more electricity trading centres have been set up in order to provide platforms for power trading.

In 2016, the Chinese coal mine industry focused on reducing excessive industrial capacity by closing small local coal mine companies and reorganising big coal mine SOEs. The NDRC also emphasised that its goal in the near future is to promote industry upgrading and transformation by reorganising big coal mine SOEs. Such an industry goal is consistent with the 13th Five Year Plan for Energy Development (2016 to 2020), pursuing a more efficient, clean and safe energy system in China.

The power reform promoted by the NDRC and the NEA has also obtained support from SOEs. A case in point is State Grid's announcement in December 2016 that it will launch a number of measures including carrying out incremental distribution of investment in business by way of mixed ownership and the relatively independent operation of trading entities.

The attempted efforts of the Chinese government to reform the energy regime in China and to introduce competition into the domestic market provides both challenges and opportunities to foreign investors interested in this market. Shale gas, for instance, is an area in which foreign investors take different views. While Shell decided to give up on its shale acreage in China, BP signed its first two PSCs for shale gas exploration, development and production in the Sichuan Basin with CNPC in March and July 2016.


The regulatory environment is changing fast in China, and the energy sector is no exception. Both the economic restructuring plan and the development of green-energy technology have had a profound influence on the energy industry. Various stakeholders and their demands contribute to innovation in the industry, while also adding complexity to the reform process. With reforms taking place in the regulatory regime and the restructuring of the market ongoing, it is vital to keep a close eye on energy regulation in China.

1 Monica Sun is a partner and Hao Su is a senior associate at Herbert Smith Freehills LLP.